Dear Reader, If you use ANSWERTRIVIA a lot, this message is for you. We're sure you are busy so we'll make this quick: Today we need your help. We don't have salespeople. We depend on donations from exceptional readers, but fewer than 2% give. If you donate just a coffee, lunch or whatever you can today, ANSWERTRIVIA could keep thriving. Thank you.
(Secure PayPal)
*Everything counts! No minimum threshold!
Thank you for inspiring us!

Enter Another Question

2/25/21

[Answer] The customer on a project tells project manager they have run out of money to pay for the project. What should the project manager do first?A. Shift more of the work to later in the schedule to allow time for customer to get the funds.B. Close project or phase.C. Stop workD. Release part of the project team

Answer: B. Close project or phase.




Most relevant text from all around the web:


The customer on a project tells project manager they have run out of money to pay for the project. What should the project manager do first?A. Shift more of ...


Disclaimer: 

Our tool is still learning and trying its best to find the correct answer to your question. Now its your turn, "The more we share The more we have". Comment any other details to improve the description, we will update answer while you visit us next time...Kindly check our comments section, Sometimes our tool may wrong but not our users.


Are We Wrong To Think We're Right? Then Give Right Answer Below As Comment

No comments:

Post a Comment