Dear Reader, If you use ANSWERTRIVIA a lot, this message is for you. We're sure you are busy so we'll make this quick: Today we need your help. We don't have salespeople. We depend on donations from exceptional readers, but fewer than 2% give. If you donate just a coffee, lunch or whatever you can today, ANSWERTRIVIA could keep thriving. Thank you.
(Secure PayPal)
*Everything counts! No minimum threshold!
Thank you for inspiring us!

Enter Another Question

2/25/21

[Answer] A project is plagued by changes to the project charter. Who has the primary responsibility to decide if these changes are necessary?A. The project managerB. The project teamC. The sponsorD. The stakeholders

Answer: C. The sponsor




Most relevant text from all around the web:


A project is plagued by changes to the project charter. Who has the primary responsibility to decide if t...


Disclaimer: 

Our tool is still learning and trying its best to find the correct answer to your question. Now its your turn, "The more we share The more we have". Comment any other details to improve the description, we will update answer while you visit us next time...Kindly check our comments section, Sometimes our tool may wrong but not our users.


Are We Wrong To Think We're Right? Then Give Right Answer Below As Comment

No comments:

Post a Comment